In just the past week, Elford Inc. completed the installation of the Acoustical Ceiling in the Embryology Lab, Endocrine/Andrology, and Procedure Room. They also finished installing the televisions, shelving and stanchion, nitrogen and carbon dioxide manifold, sanitary disposal, transaction window, and cubicle curtain. The exterior signage will be placed in the upcoming weeks and they will be doing a final clean in the lab and Procedure Room spaces.
The full project was designed by Mulrooney architecture + design and construction will be completed by Elford Inc.